California’s ‘zonal’ approach could revamp clean energy planning, shrink interconnection queue: experts

California energy experts generally agree that the state’s interconnection processes need a broad overhaul, since CAISO’s queues are overwhelmed with hundreds of requests every year

California energy experts generally agree that the state’s interconnection processes need a broad overhaul, since CAISO’s queues are overwhelmed with hundreds of requests every year from potential developers. The latest window for applications was this April, and the system operator received a total of 546 applications, amounting to 354,000 MW of new resources.

While a previous proposal from CAISO called for 46 transmission projects estimated to cost $9.3 billion, the final version approved by the board of governors last week left out one project pending additional analysis. The vast majority of these projects will be built in California and each costs between $4 million and $2.3 billion, according to the ISO.

Click here to read the full article
Source: Utility Dive

If you have any questions or thoughts about the topic, feel free to contact us here or leave a comment below.

0 replies

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *